We have recently concluded our turbine base works at the Coire Na Cloiche Wind Farm site in the Scottish Highlands. This 13 turbine development, completed in a 7-week programme saw steel fixing finished in just 5 weeks with up to 4 concrete base pours in one week. The photo shows the early stages of rebar setting out at the beginning of the project.