The pre cast section of the mooring dolphin at EDF Fife has been lifted into its offshore position and the concrete pours for the internal area have commenced. The location of the dolphin means that traditional concrete pumping methods are not possible so a barge is required to carry several skips of concrete from the quayside out to the site. This process is then repeated numerous times until the structure is complete.