Works have recently been completed at the Bhlaraidh Wind Farm site. After an exceptional effort from the Murform operates we were able to deliver the finished works well ahead of schedule, given the remote location of the project and the somewhat harsh weather conditions faced on site this showed tremendous determination from all involved.
The project concluded with the successful run of concrete works which has seen approximately 17,000m³ placed over the last 17 weeks to the 32 wind turbine foundations on site.
This has been another successful project for Murform working in partnership with main contractor RJ McLeod who were pleased with our continuing effort and commitment to the project.
The client Scottish & Southern Energy had this to say about Murform’s involvement in the project “On behalf of SSE, can I just say how impressed we were with Murform. It was my first experience of working with them and they are without a doubt the best steel fixers I have ever seen. Congratulations to all concerned in bringing the foundations in nearly 6 months earlier than predicted by the programme”