News Feed

Great Yarmouth Marina Centre

Great Yarmouth Marina Centre

Acrabuild

Works have recently started at the new Marina Centre on the Golden Mile in Great Yarmouth.  This exciting new state-of-the-art complex will provide a wide variety of community sports and leisure facilities.

The building will feature a six-lane 25m pool with full disabled access and seating for 120 spectators, a confidence water area and learner pool with a moveable floor, fun play features including flumes and splash pad as well as full changing facilities. Also, a 100-station health and fitness gym, multi-purpose sports hall, indoor climbing zone, and café as well as ample on-site car parking.

Murform will carry out the construction of all in-situ concrete, formwork and reinforcement works to the building which will involve the following:

  • In-situ Undercroft Basement.
  • In-situ Pad Foundations.
  • Casting in holding down bolt assemblies for structural steel frame of which will be installed by others.
  • Approximately 1,000m² of in-situ concrete basement and pool in-situ slabs.
  • Approximately 3,828m² of in-situ concrete ground floor slab.
  • Approximately 2,400m² of first floor in-situ concrete slab and roof poured on metal decking with the decking installed by another contractor.
  • In-situ concrete Walls & Columns to undercroft basement and pools.

The total Reinforcement will be approximately 540 tonnes with mesh in approximately 2,400m² of first floor/roof slabs.

The new Marina Centre is scheduled to open in summer 2022.