The Sheerness Recycling Plant in Sittingbourne is a multifaceted project for clients Walker Construction.
Murform carried out the structural engineering works to construct reinforced concrete foundations, slabs, and walls, these areas will be used for stockpiling of granular materials. Water and fluid tanks, a vehicular ramp for earth-moving plant, and reinforced concrete support walls and plinths for machinery and plant were also constructed.
A complex project, the heights of the required water tanks and stockpiles of stored granular material are such that considerable loads will be imposed on the supporting foundations and floor slabs. The heights of some of the support and retaining walls vary from 2.2 to 8.5m in height.
The following are approximate quantities of materials for the construction of the slabs & walls:
This project stands as a remarkable testament to engineering excellence, skillfully blending expertise and precision to fulfil the complex requirements of a modern recycling facility.
Waste
Walker Construction
Sittingbourne
£1.3m